Project dashboard
Live commercial position — edits in the Bill of Quantities flow straight through here
Cost by division Lump-Sum
Cost composition
Division summary all bases
Bill of quantities & cost build-up
Edit any amount in the highlighted column — subtotals, totals and the dashboard update instantly
Rate library
Central, reusable, versioned rates — editable and shared across projects
Pricing & margin
Set a target margin — the offer is derived from the live cost instantly
Construction cost (incl. PS)
Target margin
on selling price
Resulting offer
Margin value
Margin slider
Submitted offer was AED 874.3M at 22.0% on the lump-sum basis. Offer = cost ÷ (1 − margin%).
Value engineering
Toggle options to see the live impact on the submitted offer
Lump-sum offer
AED 874.3M
VE savings selected
−AED 20.5M
VE offer
AED 853.8M
Value-engineering options
Benchmarks
Cost intensity vs a comparable project — the dataset that compounds with every tender
Cost rate / BUA
420 AED/sqft
live, incl. PS
Concrete volume
72,127 m³
actual vs 66,386 BOQ (+8.6%)
Concrete / BUA
0.48 m³/m²
Rebar (super)
173 kg/m³